Sine-wave IPS suits fans and lights; pick one with UPS mode for computers. Tubular batteries last longer. Match charging current to ~10% of Ah — about a 13A charger for 133 Ah.
Frequently asked questions
How is IPS size found?
VA = load ÷ 0.8 (power factor). 400W needs 500 VA, rounded up to multiples of 50.
What Ah battery do I need?
Ah = load × hours ÷ 12 ÷ battery count. 400W × 4h = 1,600Wh; one battery means 133 Ah.
What if I use 2 batteries?
Each carries half — 66.5 Ah each above. Let the technician wire for your system voltage.
Can it run a fridge or motor?
They draw 3–5× at startup. For heavy loads consider solar or a generator instead of IPS.
What if backup drops?
Check water/charge; replace at 3–4 years old. Less load also stretches backup.