Formula
Sheets per row (one side) = roof width ÷ 2.33 ft (round up) Total sheets = per-row × slopes (1/2) + wastage % Bundles = total sheets ÷ pieces per bundle (round up)
- A sheet is nominally 32 inches wide but covers ≈ 28 inches = 2.33 ft after side overlap.
- 1 ban = 72 ft (70 ft for 7/10 ft sheets). Pieces per bundle = 72 (or 70) ÷ sheet length.
- There is no fixed wastage rate — the calculator defaults to 10%, change it freely.
Example
A 30×20 ft double-slope roof, 8 ft sheets, 10% extra:
Sheets per row per side = 20 ÷ 2.33 = 8.57 → 9. Double slope: 9 × 2 = 18, with 10% extra ceil(19.8) = 20 sheets. At 72 ÷ 8 = 9 pieces a bundle, bundles = 20 ÷ 9 = 2.22 → 3 bundles.
At the default Tk 8,300/bundle (PHP plain 0.42 mm), tin cost = 3 × Tk 8,300 = Tk 24,900.
With accessories: screws ≈ 125 × 3 = 375 pcs (count only), ridge ≈ Tk 55 × 30 ft = Tk 1,650, labour ≈ Tk 1,250 × 3 = Tk 3,750. Grand total = 24,900 + 1,650 + 3,750 = Tk 30,300.
Example 2 – a small single-slope room: 12 ft long, 10 ft wide, 12 ft sheets, 10% extra.
Per row = 10 ÷ 2.33 = 4.29 → 5. Single slope: 5 × 1 = 5, with 10% extra ceil(5.5) = 6 sheets. A 12 ft sheet gives 72 ÷ 12 = 6 pieces a bundle, so 6 ÷ 6 = 1 → 1 bundle, Tk 8,300 at the default price. At 0% wastage you need 5 sheets, still 1 bundle: the calculator always counts whole bundles. If a shop sells single pieces, buying 5–6 may be enough there.
Example 3 – same roof, different sheet length: a 30×20 ft double-slope roof, 10% extra. You need 20 sheets in every case, but how many pieces make a bundle depends on the length:
| Sheet length | Pieces per bundle | Bundles | Cost (Tk 8,300 a bundle) |
|---|---|---|---|
| 6 ft | 12 | 2 | Tk 16,600 |
| 8 ft | 9 | 3 | Tk 24,900 |
| 9 ft | 8 | 3 | Tk 24,900 |
| 12 ft | 6 | 4 | Tk 33,200 |
The bundle price is held equal for every length here. If your shop prices lengths differently, enter that price and compare. Also note that the calculator does not check whether the sheet length suits the slope of your roof; measure that and settle it with your mason.
Bundle and price table
| Sheet length | Pieces per bundle | Bundle feet |
|---|---|---|
| 12 ft | 6 | 72 ft |
| 9 ft | 8 | 72 ft |
| 8 ft | 9 | 72 ft |
| 6 ft | 12 | 72 ft |
| 10 ft | 7 | 70 ft |
| 7 ft | 10 | 70 ft |
Default per-bundle prices (single dealer — replace with yours): PHP plain 0.42 mm Tk 8,300 · PHP plain 0.32 mm Tk 6,290 · PHP plain 0.22 mm Tk 5,020 · PHP colour 0.42 mm Tk 9,200 · AKS plain 0.42 mm Tk 8,100 · AKS plain 0.32 mm Tk 6,050 · AKS plain 0.19 mm Tk 4,250 · AKS colour 0.42 mm Tk 9,250.
Common mistakes and practical tips
- Don’t swap length and width. Sheets are counted from the “width” box. Entering 20×30 instead of 30×20 changes the answer: 13 sheets per row, 26 in all, 29 with 10% extra, and 4 bundles of 8 ft sheets (instead of 20 sheets and 3 bundles). Follow the box labels and check the count against your mason’s.
- Rounding goes up in three places: sheets per row (8.57 → 9), total sheets after wastage (19.8 → 20) and bundles (2.22 → 3). So the bundle count tends to run a little high. Three bundles hold 27 pieces and you need 20, which leaves 7 spare.
- Don’t set wastage to zero. 0% means not one sheet is cut wrongly or damaged. The default is 10%; raise it for a crooked roof or one with windows and chimneys.
- The default price is not your local price. Type the shop’s price into the price box, otherwise the total is only a rough guide.
- Screws, ridge and labour count only when ticked. Screws appear as a count and add nothing to the cost; ridge and labour use default amounts, so check those against local quotes too.
- The roof frame is a separate cost. Timber, bamboo, angle iron and posts are not included. For the whole-house budget see house construction cost, for wall materials brick, cement and sand, and for steel weights the rod calculator.
What to know in Bangladesh
- Effective width is what counts: shops say 32 inches, but overlap leaves ≈ 28–30 inches. Measure the roof width and divide by that.
- Know brands by their mark: Abul Khair (cow), PHP Arabian Horse (horse); Jalalabad sells by SBW/weight, not mm.
- Never trust one shop’s price: defaults are one dealer’s (September 2026). Prices move with area, thickness and season — ask 2–3 shops.
- End-lap is separate: no reliable figure exists for overlap along the slope — agree it with your mason and fold it into the wastage %.
- Rough cross-checks: a 10×12-haath house ≈ 3–4 bundles, 15×20 ft ≈ 7–8, 20×30 ft ≈ 12–14 (dealers’ rules of thumb — slopes vary).
More: slope, overlap and wastage
Sheets run down the roof slope — the long side covers the slope, the wide sides join edge to edge. So the sheet count comes from the roof width, not its length. The length feeds the ridge-cap and labour estimates instead.
Side overlap eats one corrugation, so a 32-inch sheet covers ≈ 28 inches. Front-back overhang and end-lap along the slope differ per house — no reliable standard was found, so instead of a fixed constant the calculator lets you fold all of it into the wastage %. Use up to 15% for cut-up or crooked roofs; 5–10% is enough for a straight new roof.
No reliable mm–gauge–SBW conversion table was found, so this page ships none. Ask the shop for both mm and SBW and compare.