Enter the 12 item quantities (keep 0 for work you have none of).
Give the count of identical floors — foundation once, the other 7 items multiply.
Add cement, sand, aggregate, brick and rod rates plus sanitary-electrical sums for the total cost.
How it estimates
Group
Items
Floors
Once
Earthwork, sand fill, brick soling, lean 1:3:6, foundation RCC 1:1.5:3
× 1
Per floor
Frame RCC 1:2:4, 5″ brickwork, inner/outer plaster, floor/wall tiles, rod
× floors
Lump sums
Sanitary and electrical per floor; miscellaneous once
—
Examples: 1, 2 and 6 storeys (~1,000 sq ft per floor)
Material
1 storey
2 storeys
6 storeys
Cement
624 bags
1,034 bags
2,675 bags
Sylhet sand
1,143 cft
1,836 cft
4,608 cft
Local sand
2,240 cft
2,905 cft
5,566 cft
Aggregate
2,286 cft
3,672 cft
9,216 cft
Bricks
18,900
34,020
94,500
Rod
8,400 kg
16,800 kg
50,400 kg
Base quantities (once): earthwork 2,000, sand fill 1,500, soling 1,200 sft, lean 200, foundation RCC 800 cft. Per floor: frame RCC 1,500 cft, brickwork 3,000, outer plaster 2,500, inner 4,000, floor tiles 900, wall tiles 400 sft, rod 8,000 kg (with 5% wastage).
What to know in Bangladesh
Materials without rates: the calculator shows bags, cft and pieces until you add rates; rates unlock the itemised cost and grand total.
Fixed mixes: lean 1:3:6, foundation 1:1.5:3, frame 1:2:4, masonry and plaster 1:4 — the usual ratios.
Labour is separate: mason, helper and shuttering wages are outside this estimate — add per your contract.
Drawings are final: the real BOQ comes from drawings; this is an early budget and bargaining figure.
More: soling and tiles
Brick soling counts 3 bricks per sft (with wastage). Tiles are area × rate — keep mortar, pointing and labour inside the rate or add to miscellaneous.
Sanitary and electrical multiply per floor; miscellaneous (gas/water/power connections) counts once.
Frequently asked questions
What multiplies with floors?
RCC slab/beam/column, 5″ brickwork, inner and outer plaster, floor and wall tiles, and rod — 7 items. Earthwork, sand fill, soling, lean concrete and foundation RCC count once.
What mixes does the concrete use?
Lean 1:3:6, foundation 1:1.5:3, frame 1:2:4 — at 1.54 dry volume with 1 bag = 1.25 cft.
Why two kinds of sand?
Sylhet sand for concrete, local sand for masonry, plaster and filling — priced separately, so both rates exist.
Is labour included?
Only earthwork labour at your own rate. Mason and helper wages stay outside — add them under miscellaneous or separately.
Are there 1, 2 and 6-storey examples?
Yes — the material tables below use one (~1,000 sq ft per floor) example; the numbers come straight from the calculator's defaults.
Also searched as
house construction BOQ bd · six storey building estimate · building material estimate per floor