Building Estimate Calculator

Enter work quantities and unit rates. Foundation counts once; per-floor work multiplies by floors — with 1/2/6-storey examples.

Quantities (work measurements)

Once (foundation)

cft
cft
sft
cft
cft

Per floor (multiplied by floors)

cft
sft
sft
sft
sft
sft
kg

Foundation once; slab, brickwork, plaster, tiles and rod multiply by floors

%

Usually 5% on cement, sand, aggregate, bricks and rod

Unit rates (cost stays zero without prices)
৳
৳
৳
৳
৳
৳
৳
৳
৳
Sanitary, electrical and others (lump sums)
৳
৳
৳

Total cost

624 bags · 3,383 cft sand · 18,900 · 8,400 kg rod

Earthwork (2,000 cft)
৳0
Sand filling (1,500 cft)
৳0
Brick soling (1,200 sft)
৳0
Lean concrete (1:3:6) (200 cft)
৳0
RCC foundation (1:1.5:3) (800 cft)
৳0
RCC slab/beam/column (1:2:4) (1,500 cft)
৳0
5″ brickwork (3,000 sft)
৳0
Outer plaster (2,500 sft)
৳0
Inner plaster (4,000 sft)
৳0
Floor tiles (900 sft)
৳0
Wall tiles (400 sft)
৳0
Rod (MS) (8,000 kg)
৳0
Cement
624 bags
Sylhet sand (concrete)
1,143 cft
Local sand (masonry, plaster, fill)
2,240 cft
Stone chips
2,286 cft
Bricks
18,900
Rod
8,400 kg
Grand total
৳0

Total materials: 624 bags · 3,383 cft sand · 18,900 · 8,400 kg rod. Add unit rates to see the cost.

How this was calculated
  1. Foundation once; slab, brickwork, plaster, tiles and rod × 1 floors.
  2. Earthwork: 2,000 cft = ৳0.
  3. Sand filling: 1,500 cft = ৳0.
  4. Brick soling: 1,200 sft = ৳0.
  5. Lean concrete (1:3:6): 200 cft = ৳0.
  6. RCC foundation (1:1.5:3): 800 cft = ৳0.
  7. RCC slab/beam/column (1:2:4): 1,500 cft = ৳0.
  8. 5″ brickwork: 3,000 sft = ৳0.
  9. Outer plaster: 2,500 sft = ৳0.
  10. Inner plaster: 4,000 sft = ৳0.
  11. Floor tiles: 900 sft = ৳0.
  12. Wall tiles: 400 sft = ৳0.
  13. Rod (MS): 8,000 kg = ৳0.
  14. Total materials: 624 bags cement, 1,143 Sylhet sand, 2,240 local sand, 2,286 cft chips; 18,900 bricks, 8,400 kg rod.
  15. 5% wastage on materials (not on labour or lump sums).
  16. Items ৳0 + others ৳0 = grand total ৳0.

How to use

  1. Enter the 12 item quantities (keep 0 for work you have none of).
  2. Give the count of identical floors — foundation once, the other 7 items multiply.
  3. Add cement, sand, aggregate, brick and rod rates plus sanitary-electrical sums for the total cost.

How it estimates

Group Items Floors
Once Earthwork, sand fill, brick soling, lean 1:3:6, foundation RCC 1:1.5:3 × 1
Per floor Frame RCC 1:2:4, 5″ brickwork, inner/outer plaster, floor/wall tiles, rod × floors
Lump sums Sanitary and electrical per floor; miscellaneous once —

Examples: 1, 2 and 6 storeys (~1,000 sq ft per floor)

Material 1 storey 2 storeys 6 storeys
Cement 624 bags 1,034 bags 2,675 bags
Sylhet sand 1,143 cft 1,836 cft 4,608 cft
Local sand 2,240 cft 2,905 cft 5,566 cft
Aggregate 2,286 cft 3,672 cft 9,216 cft
Bricks 18,900 34,020 94,500
Rod 8,400 kg 16,800 kg 50,400 kg

Base quantities (once): earthwork 2,000, sand fill 1,500, soling 1,200 sft, lean 200, foundation RCC 800 cft. Per floor: frame RCC 1,500 cft, brickwork 3,000, outer plaster 2,500, inner 4,000, floor tiles 900, wall tiles 400 sft, rod 8,000 kg (with 5% wastage).

What to know in Bangladesh

  • Materials without rates: the calculator shows bags, cft and pieces until you add rates; rates unlock the itemised cost and grand total.
  • Fixed mixes: lean 1:3:6, foundation 1:1.5:3, frame 1:2:4, masonry and plaster 1:4 — the usual ratios.
  • Labour is separate: mason, helper and shuttering wages are outside this estimate — add per your contract.
  • Drawings are final: the real BOQ comes from drawings; this is an early budget and bargaining figure.
More: soling and tiles

Brick soling counts 3 bricks per sft (with wastage). Tiles are area × rate — keep mortar, pointing and labour inside the rate or add to miscellaneous.

Sanitary and electrical multiply per floor; miscellaneous (gas/water/power connections) counts once.

Frequently asked questions

What multiplies with floors?

RCC slab/beam/column, 5″ brickwork, inner and outer plaster, floor and wall tiles, and rod — 7 items. Earthwork, sand fill, soling, lean concrete and foundation RCC count once.

What mixes does the concrete use?

Lean 1:3:6, foundation 1:1.5:3, frame 1:2:4 — at 1.54 dry volume with 1 bag = 1.25 cft.

Why two kinds of sand?

Sylhet sand for concrete, local sand for masonry, plaster and filling — priced separately, so both rates exist.

Is labour included?

Only earthwork labour at your own rate. Mason and helper wages stay outside — add them under miscellaneous or separately.

Are there 1, 2 and 6-storey examples?

Yes — the material tables below use one (~1,000 sq ft per floor) example; the numbers come straight from the calculator's defaults.

Also searched as

house construction BOQ bd · six storey building estimate · building material estimate per floor