Roof Slab Steel Calculator

Enter the slab size and get both methods side by side. A 50 × 30 ft, 5 in slab needs ≈ 2,081 kg by shortcut, ≈ 2,068 kg detailed (12 mm at 5″ spacing).

ft
ft
in

Ordinary roofs are 5 in; sunshades 3–4 in

Shortcut method only — 1.5% is the usual assumption

Shortcut steel percentage
Bar diameter (mm)
Bar spacing

Centre to centre — usually 5–7 in for roofs

%

Lapping, cutting and binding — usually 5–10%

৳

Buy (detailed + wastage)

2,068.28 kg

Slab area
1,500 sq ft
Concrete volume
625 cft
Shortcut (% rule)
2,081.25 kg (2.081 t)
Number of bars
121 + 73
Total rod (in feet)
7,280 ft
Per foot
0.271 kg
Detailed (by spacing)
1,969.79 kg
Buy 40-ft rods
192
In tons
2.068 t

Buy about 2,068.28 kg of rod for this roof (shortcut gives 2,081.25 kg).

How this was calculated
  1. Area = 50 × 30 = 1,500 sq ft.
  2. Volume = 1,500 × 5 in ÷ 12 = 625 cft.
  3. Shortcut: 625 × 1.5% × 222 = 2,081.25 kg.
  4. Bars = (length ÷ spacing + 1) + (width ÷ spacing + 1) = (50 × 12 ÷ 5 + 1) + (30 × 12 ÷ 5 + 1) = 121 + 73.
  5. Total length = 121 × 30 + 73 × 50 = 7,280 ft.
  6. Weight = 12² ÷ 532.2 = 0.2706 kg/ft; 7,280 × 0.2706 = 1,969.79 kg.
  7. With 5% wastage: 1,969.79 + 5% = buy 2,068.28 kg.

How to use

  1. Enter the slab length and width in feet and the thickness in inches (usually 5).
  2. Pick the shortcut steel percentage (usually 1.5%).
  3. Pick the bar diameter and spacing; keep 5% wastage for lapping and cutting.

Both formulas

Method Formula Example (50 × 30 ft, 5″)
Shortcut Volume × steel% × 222 625 × 1.5% × 222 = ≈ 2,081 kg
Detailed Bars = side ÷ spacing + 1 (both ways) 121 + 73 bars = 7,280 ft
Weight Total feet × dia² ÷ 532.2 7,280 × 0.271 = ≈ 1,970 kg
To buy Detailed + wastage% With 5%: ≈ 2,068 kg (192 forty-foot rods)

Examples

1,500 sq ft roof (50 × 30, 5″, 12 mm, 5″ spacing): shortcut 625 × 0.015 × 222 = ≈ 2,081 kg (2.08 t). Detailed: 121 bars of 30 ft + 73 bars of 50 ft = 7,280 ft × 0.271 ≈ 1,970 kg, ≈ 2,068 kg (2.07 t) with 5% wastage.

1,000 sq ft roof (5″, 1.5%): 1,000 × 5 ÷ 12 × 1.5% × 222 = ≈ 1,388 kg (1.39 t).

Weight by diameter

Diameter kg/ft One 40 ft rod
10 mm 0.188 7.52 kg
12 mm 0.271 10.82 kg
16 mm 0.481 19.24 kg

What to know in Bangladesh

  • Both are estimates, not designs: use the shortcut for budgeting and the detailed figure plus the engineer’s drawing for buying.
  • Usual values: 5 in slab, 10–12 mm bars, 5–7 in spacing, 1–2% steel (usually 1.5%).
  • Don’t forget lapping: long roofs need joined bars — cover it inside wastage (5–10%).
  • Beams and columns are extra: this is slab mesh only; beams, columns, drops and stairs are separate.
More: where 222 and 532.2 come from

One cubic foot of mild steel (density ~7,850 kg/m³) weighs ≈ 222 kg — hence the shortcut multiplies the steel share of the volume by 222.

Per metre a bar weighs dia² ÷ 162.2 kg; with 1 ft = 0.3048 m that is dia² ÷ 532.2 kg per foot. Masons often say dia² ÷ 533; the result is almost the same.

Round fractional bar counts up (86.7 → 87) before adding 1 — the calculator always rounds up this way.

Frequently asked questions

What is the shortcut formula?

Volume × steel% × 222 = kg. A 50 × 30 × 5″ slab is 625 cft, so 625 × 1.5% × 222 ≈ 2,081 kg (2.08 t).

What is the detailed (spacing) formula?

Bars each way = (side ÷ spacing) + 1. At 5″ spacing a 50 ft side needs 121 bars of 30 ft and the 30 ft side needs 73 bars of 50 ft — 7,280 ft in total. Weight = feet × dia² ÷ 532.2.

How much does rod weigh per foot?

Dia² ÷ 532.2 kg. 10 mm is 0.188, 12 mm is 0.271 and 16 mm is 0.481 kg/ft.

Will the two methods agree?

Roughly, never exactly. The shortcut is a quick estimate; buy on the detailed figure — this page shows both so you can cross-check.

How much wastage should I add?

5–10% for lapping, cutting and binding. The calculator adds wastage to the detailed figure only; the shortcut is already approximate.

Does this include beams and columns?

No — slab mesh only. Beams, columns, stairs and extra laps come from the structural drawing. The engineer's bar bending schedule is final.